Insurance Company cannot raise delay as a Ground for Repudiation

Insurance Company cannot raise delay as a Ground for Repudiation

Kritika Pandey | Maharaja Sayajirao University of Baroda | 24th December 2019 

Saurashtra Chemicals Ltd. (Presently known as Saurashtra Chemicals Division of Nirma Ltd.) v. National Insurance Co. Ltd Civil Appeal No. 2059 of 2015

FACTS:

  • The appellant purchased a standard fire and special perils policy from the respondent National Insurance Company Ltd. thereby insuring the risk of loss/damage to the stock of coal and lignite stored in its factory compound. An additional premium was paid by the appellant company so as to cover the risk of loss of the aforesaid stock on account of spontaneous combustion. The appellant was declared a Sick Unit and was accordingly registered under SICA. The factory remained closed from 17.02.2006 to 09.08.2006 and was re-opened on 10.08.2006.
  • After re-opening it was noticed between the period from 11.8.2006 to 20.8.2006 that some amount of stock of coal and lignite has been diminished/destroyed on account of spontaneous combustion, causing loss and damage. Intimation in this regard was sent to the respondent-insurer on 12.09.2006.
  • Pursuant to the claim made, a surveyor was appointed who visited the premises of the appellant and sought certain details.After carrying out the requisite survey, the surveyor submitted his report assessing total loss to the tune of Rs.63,43,679/-.
  • The claim lodged by the appellant was however repudiated by the respondent-insurer on the ground that since spontaneous combustion did not result into fire thus, there is no liability under the policy.
  • On denial of the claim the appellant approached the National Consumer Disputes Redressal Commission (hereinafter referred to as the NCDRC).
  • The complaint was resisted by the Insurer on the ground that:-

(i) No claim was payable under the terms and conditions on which policy was issued inasmuch as destruction or damage, if any, caused to the property by fire on account of its own fermentation, natural heating or spontaneous combustion or undergoing natural heating or drying process is not covered.

(ii) Intimation of claim was sent with considerable delay of over a month thereby violating condition no. 6(i) of the General Conditions of Policy.

  • Under Clause 6(i) the intimation of loss and damage was required to be given in writing by way of notice within 15 days of the occurrence thereof. It is an admitted case between the parties that intimation of loss/damage was given by the appellant to the respondent insurer for the first time on 12.09.2006.

NCDRC HELD

  • The NCDRC rejected the claim holding that since the complainant (Appellant herein) had contravened Clause 6(i) of the General Conditions of Policy, no claim is payable.

ISSUES RAISED

  • Whether the respondent-insurer had waived the condition relating to delay in intimation and lodging of the claim, by appointing a surveyor.
  • Whether in the absence of any mention, of aspect of delay in intimation and violation of conditions of Clause 6(i) of General Conditions of Policy, in the repudiation letter, the same could be taken as defence before the NCDRC.

HELD

  • By appointing a surveyor the respondent insurer is estopped from raising the plea of violation of condition prescribing a time limit for intimation/lodging of the claim, has no legs to stand.
  • There was no reference of delay in intimation or lodging of the claim as stipulated in Clause 6(i) of the General Conditions of Policy in the repudiation letter.
  • The NCDRC has failed to take into consideration this aspect of the matter and, therefore, cannot be held to be justified in rejecting the claim of the appellant, on that ground.
  • In view of the aforesaid analysis the appeal stands allowed and the impugned judgment and the order of the NCDRC is set aside.
  • The Respondent insurer is directed to make payment of Rs. 63,43,679/-, as assessed by the surveyor, to the appellant with interest @ 8% from the date of the filing of the claim of petition till date of payment. The payment, as above, be made within eight weeks from today.

560 315 LexForti Legal News Network
Share

Leave a Reply

Avatar

LexForti Legal News Network

LexForti Legal News and Journal offer access to a wide array of legal knowledge through the Daily Legal News segment of our Website. It provides the readers with the latest case laws in layman terms. Our Legal Journal contains a vast assortment of resources that helps in understanding contemporary legal issues.

All stories by : LexForti Legal News Network
About Author
Avatar

LexForti Legal News Network

LexForti Legal News and Journal offer access to a wide array of legal knowledge through the Daily Legal News segment of our Website. It provides the readers with the latest case laws in layman terms. Our Legal Journal contains a vast assortment of resources that helps in understanding contemporary legal issues.

Consult
Leave this field blank
CLICK HERE TO VISIT